Wednesday, August 8: Remove driveway ramps and set string line for curb installation on the North side of Greenview and the East side of Briar Place.

Thursday, August 9: Pour curb on above locations.

Friday, August 10: Remove, frame and pour driveways on above locations.

Monday, August 13: Access to driveways on above locations restored.

Please remember: this is a tentative schedule and always possible to change. The biggest factor is the weather, and this rain isn't helping out right now. We will do the best we can to keep everyone informed!

The contractor asks that residents park on nearby streets on the day they pour curb. Once the curb is poured, residents are allowed to park on that street.