Tuesday, October 23, 2007

THANK YOU!

Well, we're down to the nitty-gritty on the project: final touches, walk-through, final acceptance, etc. Thank you to all the residents for being so cooperative and understanding! It was greatly appreciated!

Some Before and After Photos





Wednesday, October 10, 2007

Surface Complete!

The surface asphalt was completed on Monday, October 8. All that remains now are a few spots that need sod and the retaining wall.

Surface Notice

The Contractor is scheduled to place the surface level of asphalt on Monday, October 8, 2007 (weather permitting). For this process, a prime coat (sticky tack) will be placed on the existing surface in order to create a bond between the binder and surface levels of pavement. This tack is very sticky and if driven over, can track onto your driveways. The prime coat will be applied at approximately 5:00 A.M. on Monday morning. It takes a couple of hours to cure. However, to avoid any damage to vehicles or driveways, we strongly recommend you park on surrounding streets beginning Sunday evening if you will need your car Monday morning. As soon as the surface is placed and compacted, you will be allowed to drive on it. ALSO, please allow extra time for possible delays as you leave/return to your homes.

Monday, October 1, 2007

Sod and Retaining Wall

A. Lamp began placing sod this morning and should be done by Friday.

Work has begun on the Modular Retaining Wall at the corner of Greenview and Arlington Heights. This should take all week to complete.

Once both these tasks are complete, the final lift of asphalt will be placed. As of right now, that is scheduled for Monday, October 8.

Tuesday, September 11, 2007

Nearing the end...

Only a few tasks are left to complete the project: parkway restoration and the final lift of asphalt. If the weather stays like it is now (cool and gorgeous!) A. Lamp will plan on placing sod sometime next week with asphalt the following week.

Friday, September 7, 2007

Alley Complete!

The alley was paved with both binder and surface yesterday, just in time for the rain. Everything looks great. The contractor will do a small amount of parkway restoration to clean up the edges.