Monday, October 1, 2007

Sod and Retaining Wall

A. Lamp began placing sod this morning and should be done by Friday.

Work has begun on the Modular Retaining Wall at the corner of Greenview and Arlington Heights. This should take all week to complete.

Once both these tasks are complete, the final lift of asphalt will be placed. As of right now, that is scheduled for Monday, October 8.