Wednesday, September 5, 2007

This Week's Schedule

Wednesday-Friday: Structure Adjustments
Thursday: Pave Alley

Next week: Sod and surface (hopefully!)


What's a structure adjustment?
All the structures (manholes) that are in the roadway were covered by the binder level of asphalt. The contractor comes back in, digs up the structure covers and raises them to the appropriate height, closing in the hole with concrete. So until the surface level is placed, the structure frames will be slightly higher than the road.

No comments: